Dependencies


Du er her: InLoox Project management glossary Dependencies

Logische Abhängigkeit von Vorgängen

Dependencies describe the relationship between two or more sequential tasks. These relationships determine in which order the project team needs to do the tasks. Thus, the project manager needs to identify the dependencies between tasks in order to draw up the project schedule.

There are four types of dependencies:

  1. End to start: Task B can’t start until task A is finished
  2. Start to start: Task B can only start if task A has already started
  3. End to end: Task B can only finish if task A has finished
  4. Start to end: Task B can’t finish until task A starts

These dependencies are often visualized in a critical path

Sie wollen regelmäßig Infos zum Thema Projektmanagement erhalten?


Projektmanagement-Newsletter

Erfahren Sie mehr rund ums Projektmanagement auf unserem Blog


Zum InLoox Blog

Unsere Projektmanagement-Software InLoox hilft Ihnen, Projekte schneller, effizienter und sicherer zum Erfolg zu führen


Mehr erfahren

Weitere Begriffe