Dependencies describe the relationship between two or more sequential tasks. These relationships determine in which order the project team needs to do the tasks. Thus, the project manager needs to identify the dependencies between tasks in order to draw up the project schedule.

There are four types of dependencies:

  1. End to start: Task B can’t start until task A is finished
  2. Start to start: Task B can only start if task A has already started
  3. End to end: Task B can only finish if task A has finished
  4. Start to end: Task B can’t finish until task A starts

These dependencies are often visualized in a critical path